top of page

Introduction

 

Dowling Dirtworks has been involved in some of the largest projects in Victoria.

Many of these projects being the main contractor. One project undertaken,

Dowling Dirtworks supplied and managed 50 pieces of plant and machinery.

 

Take a look below to see the large list of projects they have been involved in completing.

Metro Tunnel Occupation                                                                                                                                   2018 - 2019

CPB & John Holland

In 2018 - 2019 Dowling Dirtworks was comprised to supply five Articulated Dump Trucks for the Western Entrance of the Metro Tunnel Occupational works.

Blu Project                                                                                                                                                           ongoing

Lend Lease

In 2018 Dowling Dirtworks secured work for the Ballarat Line Upgrade Project, a large ongoing project requiring the entire Ballarat Railway line to be upgraded.

Monash Freeway Upgrade                                                                                                                                  2017 - 2018

Fulton Hogan

From 2017 - 2018 Dowling Dirtworks was involved in the major bulk earthworks and the organisation of of plant on site for Fulton Hogan.

Some of the plant organised for this particular job  were; articulated dump trucks, excavators and dozers.

Thompsons Road Upgrade                                                                                                                               2017 - 2018     

BMD

2017 - 2018 Dowling Dirtworks was involved in the bulk earthworks of the Thompsons Road Upgrade with BMD.

Dowling Dirtworks has had a long and successful working relationship with BMD and is now considered one of their preferred contractors. 

Level Crossing Removal Program                                                                                                                  2016 ongoing      

CPB

2016 - 2017 Dowling Dirtworks was involved in the facilitation of the Level Crossing Removal Program.

There are many parts of the program that are on going for up until 2025 that Dowling Dirtworks is an active contractor in facilitating the safe upgrades of Level Crossing Removals across Victoria.

Tram Works                                                                                                                                                                 May 2015 ongoing

Fulton Hogan                                                                                                                                      

 

From May 2015 Dowling Dirtworks was involved in many tram projects in Melbourne and continues to be a

preffered supplier of Fulton Hogan on tram works. The works primarily involve pulling up the tram tracks in

order for new ones to be laid. Due to the urgency of these projects often works would be carried out over a

12 hour rotating rosters working around the clock to get the maximum productivity and machine utilisation.

Some of the projects included:

 

Flinders Street, Melbourne

High Street, Melbourne

Swanston Street, Melbourne

Queensbridge Street, Melbourne

Lygon Street, Brunswick

MALRC Program                                                                                                                                                                 2014 ongoing

Fulton Hogan Ecodynamics - in Alliance with Melbourne Water                                                 

 

In 2014 Dowling Dirtworks signed a contract to work on the Melbourne Water maintenance and low risk capital program with Fulton Hogan Ecodynamics which involved the minor defects works. The contract covered from Drouin to Baccus Marsh, over the 12 month contract period Dowling Dirtworks worked on over 50 different projects. Plant supplied were tandem tippers, water cart, posi track, 13T, 16T, 25T excavators, 30T articulated dump trucks. Excavation works included rock beaching, creeks and stream rehab, caveat baskets and more.

 

In May 2015 Melbourne Water invited Dowling Dirtworks to be a preferred contractor and started contracting for Melbourne Water direct.

Burwood Development Square (former brickworks site)                                                                                                   2014 ongoing
National Logistics Plant Hire

 

Four dump trucks where supplied on this project.

 

 

Western Highway Duplication Beaufort to Buangor                                                                                                   2014 to May 2015
Lend Lease


Project Value: 95 Million

 

Dowling Dirtworks worked on this massive highway duplication and supplied 8 articulated dump trucks. This section of the highway between east of McKinnon Lane and Andersons Road was a whopping 15km and is expected to be completed in 2016.

Koo Wee Rup Bypass                                                                                                                                           Dec 2013 to May 2015
Lend Lease Engineering (Formerly Abi Group)

 

Project Value: $66 million

 

This project was the closest to home Dowling Dirtworks has been involved in. The job ran over 3.4km between the Pakenham Bypass and Manks Road in Koo Wee Rup. Various machines where provided on this job including: 12T, 20T, 25T, 30T excavators, a posi track and articulated dump trucks.The bulk of the works were completed in May 2015, six months ahead of schedule.

Bald Hill Wind Farm - Hazell Bro’s                                                                                                                         Dec 2014 to Oct 2015

 

Project Value: $400 million

 

Dowling Dirtworks was the main supplier on this job. We were able to supply approximately

50 plant and machinery with highly skilled operators across the project including:
 

Articulated Dump Trucks

Excavators

Scrapers

Dozers

Backhoes

Rollers

Water Carts

Graders

Low Loaders


 

There were some challenges along the journey with heavy rainfall and titled ground water occurring

in the southern end of the job. The landscape had extremely deep inclines in loose sandy conditions.

With planning and good supervision Dowling Dirtworks completed the works ahead of schedule with

no incidents occurring.

Regional Rail Link

Package E - Baulderstone Leighton Joint Venture

 

Project Value: $4 billion

 

In The Beginning

 

Dowling Dirtworks commenced working on site in May 2012 and were one of the very first contractors on the project.

 

To begin with we were involved in the trials on the surface minor to quantify its potential productivity and viability on the project. To carry out these trials we used GPS and on board weighing systems to calculate productivity.

 

The results showed that the surface minor had failed to produce the productivity required.

Our machines continued to work alongside the rail corridor for the remainder of the rock extraction.

 

 

Smashing Goals

 

Dowling Dirtworks organised and coordinated a fleet of machinery to complete a section near Baretta Road, North Division. Our scope of works was to move approximately 8,000m³ of very hard going rock and dirt with 24 hour rotating shifts during a 10 day rail occupation. The fleet consisted of 6 x 30T Articulated Dump Trucks.

 

In 48 hours Dowling Dirtworks had completed the bulk earthworks, an unbelievable 8 days ahead of schedule. We continued our 24 hour rotating shifts for the next 6 days and completed additional works that were not in our scope of works, putting Baulderstone weeks in advance of their schedule.

 

Through the use of state of the art technology our GPS guided machines were able to complete the works with the highest level of accuracy and precision.

                                                                     May 2012 to Jun 2014

 

 

 

The Regional Rail Link is a 47.5 km stretch of railway line under construction through the inner western suburbs of Melbourne

from Southern Cross station and meeting the Geelong line at

West Werribee. The line was built at or above ground with the

primary aim of improving grade separation and improving public transport services to the city's growing western fringe.

 

“The largest public transport

infrastructure project in Australia”

 

 

 

 

 

 

 

 

 

 

 

 

 

Dowling Dirtworks provided a fleet of 20 plant including

articulated dump trucks, dozers, excavators and graders on

the Regional Rail Link. We also played a major role in

providing a prompt and ongoing float service for this project.

 

The primary works undertaken during the project was for

Baulderstone Leighton Joint Venture on Package E however

we have worked across the whole project including:

 

Package A            John Holland

Package B            AbiGroup & John Holland

Package C           Thiess

Package E            Baulderstone Leighton Joint Venture

Package F            Leighton Downer Joint Venture

Nagambie Bypass                                                                                                                                                            2012 to 2014
Abi Group

 

Project Value: 109 million

 

The Nagambie bypass is a 13.5km dual carriageway between Mitchelstown Road and Kirwan’s Bridge-Longwood Road. Dowling Dirtworks supplied 30T articulated dump trucks on this project.

Peninsula Link – Abi Group (Now Lend Lease)                                                                                                       Mar 2010 to 2013     

  
Project Value: $759 million

 

The Peninsula link is a 27km freeway between the East Link toll road in

Melbourne's east and the Mornington Peninsula Freeway at Mt Martha.

The project was expected to reduce travel times by up to 40 minutes

compared to the previous route and will carry around 50,000 to 60,000

cars per day.

 

“It’s no surprise that Dowling Dirtworks has

accrued a long list of major project credits

during its relatively short life-span”

 

 

These are the words published by “Australian Main Roads” featured in “Construction News” Magazine whilst working on the Peninsula Link project. Dowling Dirtworks made a huge impact on this project by its ability to provide highly skilled and reliable operators along with its large fleet of machinery.

 

Dowling Dirtworks were involved in moving 3 million3 meters in cut and fills as well as other overburden and top soil placement. Dowling Dirtworks also played a major role in transportation of machines; we completed over 3,000 float shifts for Abigroup over a 3 year period on the Peninsula Link alone.

Other Projects include:

 

Project                                                                          Contractor                                           Project Value                   Year

Bass Hwy Duplication Stage 7                                      Cut & Fill                                             39.8 million                        2012

West Swanston Terminal of Melbourne                        Fulton Hogan                                      17 million                           2012
Craigiburne Train Maintenance Facility                        John Holland                                       65 million                           2012

Namatjira Wetland Construction Clayton South            Fulton Hogan                                      7.36 million                        2011

Brushy Creek Flood Protection                                     Fulton Hogan / Melbourne Water                                                  2010

Dandenong Valley Wetlands                                         EPH Melbourne Water                        15 million                          2009/2010

Kelletts Road Drain Wetland Construction Rowville      Fulton Hogan                                      5 million                            2009/2010

Geelong Ring Road Stage 3                                         Abi Group                                            110 million                        2007/2009

Loch-Bena / Bena Bypass                                            Cut & Fill                                              23 million                          2007

Brooklyn to Lara Pipeline                                              A.J.Lucas                                             50 million                         2008

Sandhurst Golf Club Community                                  BMD                                                     32 million                         2005

Craigieburn Bypass Stage 4                                        Abi Group                                             121 million                       2005

 

 

bottom of page